Dept. of Trans. PROGRESS Serial No. Contract No. 00-363-09-42 04-438614 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 77% 69% 04-SCL-237-8.0/9.6 Federal Project: 04-SCL-880-7.8/10.1 NHI-880-1(41) AC-880-1(41) ACST-S237(7) Progress payment No. 28 Payment period ending: 12-20-00 DE SILVA GATES CONSTRUCTION P O BOX 2909 DUBLIN CA 94568 Escrow No. 01171 Total Estimate This Estimate 1. Contract Itms Without Mobil. 26,858,520.58 551,218.55 2.a. Extra Work 1,669,697.89 196,882.59 b. Adjustment Comp. 437,339.79 0.00 3. Materials on Hand 366,036.15 -55,417.57 4. Earned Subject to Retention 29,331,594.41 692,683.57 5. Mobilization 3,874,000.00 0.00 6. Total Work Completed 32,839,558.26 7. Deductions -2,600.00 0.00 8. a.Contract Retentions -1,466,579.72 -34,634.18 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 31,736,414.69 658,049.39 10. Reduction Amt to Escrow 11. Payment to Escrow 1,466,570.00 12. Net Pymt. this Estimate 658,049.39