Dept. of Trans. PROGRESS Serial No. Contract No. 01-079-11-49 04-438614 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 80% 79% 04-SCL-237-8.0/9.6 Federal Project: 04-SCL-880-7.8/10.1 NHI-880-1(41) AC-880-1(41) ACST-S237(7) Progress payment No. 31 Payment period ending: 03-20-01 DE SILVA GATES CONSTRUCTION P O BOX 2909 DUBLIN CA 94568 Escrow No. 01171 Total Estimate This Estimate 1. Contract Itms Without Mobil. 27,599,508.46 392,872.21 2.a. Extra Work 2,189,169.98 -13,051.51 b. Adjustment Comp. 522,703.94 7,000.00 3. Materials on Hand 396,226.65 28,690.38 4. Earned Subject to Retention 30,707,609.03 415,511.08 5. Mobilization 3,874,000.00 0.00 6. Total Work Completed 34,185,382.38 7. Deductions -2,600.00 0.00 8. a.Contract Retentions -1,535,380.45 -20,775.55 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 33,043,628.58 394,735.53 10. Reduction Amt to Escrow 11. Payment to Escrow 1,535,380.00 12. Net Pymt. this Estimate 394,735.53