Dept. of Trans. PROGRESS Serial No. Contract No. 02-232-14-04 04-438614 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 96% 100% 04-SCL-237-8.0/9.6 Federal Project: 04-SCL-880-7.8/10.1 NHI-880-1(41) AC-880-1(41) ACST-S237(7) Progress payment No. 48 Payment period ending: 08-20-02 DE SILVA GATES CONSTRUCTION P O BOX 2909 DUBLIN CA 94568 Escrow No. 01171 Total Estimate This Estimate 1. Contract Itms Without Mobil. 37,074,318.15 882,955.73 2.a. Extra Work 4,182,101.10 54,682.66 b. Adjustment Comp. 1,124,885.36 21,000.00 3. Materials on Hand 10,854.00 -40,060.02 4. Earned Subject to Retention 42,392,158.61 918,578.37 5. Mobilization 3,874,000.00 0.00 6. Total Work Completed 46,255,304.61 7. Deductions -65,218.75 -26,400.00 8. a.Contract Retentions -2,119,607.93 -45,928.92 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 44,081,331.93 846,249.45 10. Reduction Amt to Escrow 11. Payment to Escrow 2,119,600.00 12. Net Pymt. this Estimate 846,249.45