Dept. of Trans. PROGRESS Serial No. Contract No. 07-052-08-29 04-4396U4 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 94% 100% 04-SCL-87-0.0/5.1 Federal Project: ACNH-S087(27) Progress payment No. 25 Payment period ending: 02-20-07 R G W CONSTRUCTION INC P O BOX 2910 LIVERMORE CA 94551 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 34,855,600.05 912,985.04 2.a. Extra Work 2,596,301.74 283,543.41 b. Adjustment Comp. 222,433.80 2,700.00 3. Materials on Hand 119,545.80 -79,576.55 4. Earned Subject to Retention 37,793,881.39 1,119,651.90 5. Mobilization 4,014,705.00 0.00 6. Total Work Completed 41,689,040.59 7. Deductions -7,820.00 0.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 41,800,766.39 1,119,651.90 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,119,651.90