Dept. of Trans. PROGRESS Serial No. Contract No. 04-264-11-19 04-443404 PROGRESS PAYMENT VOUCHER %complete: %time: Location: PEP SAT 04-ALA-13-5.0/5.6 Federal Project: NONE Progress payment No. 27 Payment period ending: 09-20-04 AMLAND 3168 KNIGHTS BRIDGE RD SAN JOSE CA 95132 Escrow No. 01948 Total Estimate This Estimate 1. Contract Itms Without Mobil. 313,986.80 1,620.00 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 313,986.80 1,620.00 5. Mobilization 35,000.00 0.00 6. Total Work Completed 348,986.80 7. Deductions -1,000.00 0.00 8. a.Contract Retentions -15,699.34 -81.00 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 332,287.46 1,539.00 10. Reduction Amt to Escrow 11. Payment to Escrow 15,450.00 12. Net Pymt. this Estimate 1,539.00