Dept. of Trans. AFTER ACCEPTANCE Serial No. Contract No. 06-223-11-39 04-443544 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 04-SF-101-0.5/1.8 Federal Project: NONE Progress payment No. 06 Payment period ending: 07-21-06 CALIFORNIA ENGINEERING CONTRACTORS INC 20 HAPPY VALLEY ROAD PLEASANTON CA 94566 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 231,947.95 300.00 2.a. Extra Work 41,844.67 41,844.67 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 273,792.62 42,144.67 5. Mobilization 27,000.00 0.00 6. Total Work Completed 300,792.62 7. Deductions 8. a.Contract Retentions -11,582.40 0.00 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 11,582.40 11,582.40 9. Total pay to Contractor 300,792.62 53,727.07 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 53,727.07