Dept. of Trans. PROGRESS Serial No. Contract No. 09-111-08-32 04-444214 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 6% 13% 04-NAP-121-0.3/2.1 Federal Project: ACHS-P121(22) STP-P121(22) Progress payment No. 03 Payment period ending: 04-20-09 NORTH BAY CONSTRUCTION INC P O BOX 6004 PETALUMA CA 949556004 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 159,917.65 37,623.00 2.a. Extra Work 19,567.29 518.62 b. Adjustment Comp. 3. Materials on Hand 109,484.25 70,942.32 4. Earned Subject to Retention 288,969.19 109,083.94 5. Mobilization 162,675.00 162,675.00 6. Total Work Completed 342,159.94 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 451,644.19 271,758.94 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 271,758.94