Dept. of Trans. PROGRESS Serial No. Contract No. 06-108-12-08 04-444604 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 41% 92% 04-NAP-121-9.0/9.2 Federal Project: NONE Progress payment No. 04 Payment period ending: 04-20-06 AMLAND 3168 KNIGHTS BRIDGE ROAD SAN JOSE CA 95132 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 74,525.00 7,450.00 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 74,525.00 7,450.00 5. Mobilization 19,000.00 0.00 6. Total Work Completed 93,525.00 7. Deductions -400.00 -400.00 8. a.Contract Retentions -4,135.66 0.00 b. Unsatisfactory Prog. -2,411.84 -372.50 c. Reduction after 95% Comp. 9. Total pay to Contractor 86,577.50 6,677.50 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 6,677.50