Dept. of Trans. PROGRESS Serial No. Contract No. 06-139-10-01 04-444804 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 23% 21% 04-ALA-580-R9.0/27.5 Federal Project: 04-ALA-680-R8.7/27.5 NONE 04-ALA-880-4.0/27.5 Progress payment No. 01 Payment period ending: 05-20-06 M BUMGARNER INC 1175 GREENVILLE RD LIVERMORE CA 94550 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 148,075.00 148,075.00 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 148,075.00 148,075.00 5. Mobilization 9,500.00 9,500.00 6. Total Work Completed 157,575.00 7. Deductions 8. a.Contract Retentions -13,794.45 -13,794.45 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 143,780.55 143,780.55 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 143,780.55