Dept. of Trans. PROGRESS Serial No. Contract No. 10-021-08-46 04-448804 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 57% 41% 04-SCL-152-6.1/6.7 Federal Project: ACST-P152(72) PACB-P152(72) RSTP-P152(72) Progress payment No. 11 Payment period ending: 01-20-10 R G W CONSTRUCTION INC P O BOX 2910 LIVERMORE CA 94551 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2,495,418.12 -30,054.65 2.a. Extra Work 401,502.93 204,865.61 b. Adjustment Comp. 160,000.00 0.00 3. Materials on Hand 0.00 -154,245.26 4. Earned Subject to Retention 3,056,921.05 20,565.70 5. Mobilization 498,000.00 0.00 6. Total Work Completed 3,554,921.05 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 3,554,921.05 20,565.70 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 20,565.70