Dept. of Trans. PROGRESS Serial No. Contract No. 10-263-10-57 04-448804 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 88% 81% 04-SCL-152-6.1/6.7 Federal Project: ACST-P152(72) PACB-P152(72) RSTP-P152(72) Progress payment No. 18 Payment period ending: 09-20-10 R G W CONSTRUCTION INC P O BOX 2910 LIVERMORE CA 94551 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 4,045,862.87 541,215.75 2.a. Extra Work 452,210.05 6,764.30 b. Adjustment Comp. 517,856.88 0.00 3. Materials on Hand 19,223.00 19,223.00 4. Earned Subject to Retention 5,035,152.80 567,203.05 5. Mobilization 498,000.00 0.00 6. Total Work Completed 5,513,929.80 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 5,533,152.80 567,203.05 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 567,203.05