Dept. of Trans. PROGRESS Serial No. Contract No. 12-202-14-23 04-448834 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 37% 8% 04-SCL-152-6.1/6.5 Federal Project: STP-S152(77) Progress payment No. 04 Payment period ending: 07-20-12 SUAREZ & MUNOZ CONSTRUCTION INC 20975 CABOT BLVD HAYWARD CA 94545 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 198,336.00 143,139.10 2.a. Extra Work 35,489.17 35,489.17 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 233,825.17 178,628.27 5. Mobilization 12,350.00 5,850.00 6. Total Work Completed 246,175.17 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 246,175.17 184,478.27 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 184,478.27