Dept. of Trans. PROGRESS Serial No. Contract No. 07-020-08-11 04-449404 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 2% 11% 04-SF-101-9.1/9.4 Federal Project: NONE Progress payment No. 04 Payment period ending: 01-20-07 CALIFORNIA ENGINEERING CONTRACTORS INC 20 HAPPY VALLEY ROAD PLEASANTON CA 94566 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 233,208.00 120,668.00 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 233,208.00 120,668.00 5. Mobilization 6. Total Work Completed 233,208.00 7. Deductions -27,911.50 0.00 8. a.Contract Retentions -23,320.80 -12,066.80 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 181,975.70 108,601.20 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 108,601.20