Dept. of Trans. PROGRESS Serial No. Contract No. 08-238-14-24 04-449404 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 93% 59% 04-SF-101-9.1/9.4 Federal Project: NONE Progress payment No. 23 Payment period ending: 08-20-08 CALIFORNIA ENGINEERING CONTRACTORS INC 20 HAPPY VALLEY ROAD PLEASANTON CA 94566 Escrow No. 02275 Total Estimate This Estimate 1. Contract Itms Without Mobil. 14,012,607.60 677,412.70 2.a. Extra Work 793,714.60 32,037.24 b. Adjustment Comp. 40,000.00 40,000.00 3. Materials on Hand 4. Earned Subject to Retention 14,846,322.20 749,449.94 5. Mobilization 1,365,000.00 0.00 6. Total Work Completed 16,211,322.20 7. Deductions 8. a.Contract Retentions -742,316.11 -37,472.50 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 15,469,006.09 711,977.44 10. Reduction Amt to Escrow 11. Payment to Escrow 742,310.00 12. Net Pymt. this Estimate 711,977.44