Dept. of Trans. PROGRESS Serial No. Contract No. 06-356-07-40 04-470804 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 30% 12% 04-ALA-580-0.0/2.7 Federal Project: NONE Progress payment No. 05 Payment period ending: 12-20-06 DE SILVA GATES M C M A JOINT VENTURE OF DE SILVA GATES CONSTRUCTION AND M C M CONSTRUCTION P O BOX 2909 DUBLIN CA 94568Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 3,393,763.05 527,325.66 2.a. Extra Work 765,063.60 0.00 b. Adjustment Comp. -3,000.00 0.00 3. Materials on Hand 160,360.23 68,672.53 4. Earned Subject to Retention 4,316,186.88 595,998.19 5. Mobilization 1,786,000.00 0.00 6. Total Work Completed 5,941,826.65 7. Deductions -10,000.00 10,000.00 8. a.Contract Retentions -361,882.78 0.00 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 5,730,304.10 605,998.19 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 605,998.19