Dept. of Trans. PROGRESS Serial No. Contract No. 07-022-13-28 04-470804 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 32% 13% 04-ALA-580-0.0/2.7 Federal Project: NONE Progress payment No. 06 Payment period ending: 01-20-07 DE SILVA GATES M C M A JOINT VENTURE OF DE SILVA GATES CONSTRUCTION AND M C M CONSTRUCTION P O BOX 2909 DUBLIN CA 94568Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 3,768,159.35 374,396.30 2.a. Extra Work 765,520.01 456.41 b. Adjustment Comp. -3,000.00 0.00 3. Materials on Hand 183,911.57 23,551.34 4. Earned Subject to Retention 4,714,590.93 398,404.05 5. Mobilization 1,786,000.00 0.00 6. Total Work Completed 6,316,679.36 7. Deductions -10,000.00 0.00 8. a.Contract Retentions -361,882.78 0.00 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 6,128,708.15 398,404.05 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 398,404.05