Dept. of Trans. PROGRESS Serial No. Contract No. 07-053-13-09 04-470804 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 32% 13% 04-ALA-580-0.0/2.7 Federal Project: NONE Progress payment No. 07 Payment period ending: 02-20-07 DE SILVA GATES M C M A JOINT VENTURE OF DE SILVA GATES CONSTRUCTION AND M C M CONSTRUCTION P O BOX 2909 DUBLIN CA 94568Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 3,927,888.28 159,728.93 2.a. Extra Work 765,913.68 393.67 b. Adjustment Comp. -3,000.00 0.00 3. Materials on Hand 152,563.57 -31,348.00 4. Earned Subject to Retention 4,843,365.53 128,774.60 5. Mobilization 1,786,000.00 0.00 6. Total Work Completed 6,476,801.96 7. Deductions -20,000.00 -10,000.00 8. a.Contract Retentions -361,882.78 0.00 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 6,247,482.75 118,774.60 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 118,774.60