Dept. of Trans. PROGRESS Serial No. Contract No. 07-081-09-54 04-470804 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 35% 13% 04-ALA-580-0.0/2.7 Federal Project: NONE Progress payment No. 08 Payment period ending: 03-20-07 DE SILVA GATES M C M A JOINT VENTURE OF DE SILVA GATES CONSTRUCTION AND M C M CONSTRUCTION P O BOX 2909 DUBLIN CA 94568Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 4,486,808.53 558,920.25 2.a. Extra Work 767,583.25 1,669.57 b. Adjustment Comp. -3,000.00 0.00 3. Materials on Hand 219,858.38 67,294.81 4. Earned Subject to Retention 5,471,250.16 627,884.63 5. Mobilization 1,786,000.00 0.00 6. Total Work Completed 7,037,391.78 7. Deductions -9,612.44 10,387.56 8. a.Contract Retentions -361,882.78 0.00 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 6,885,754.94 638,272.19 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 638,272.19