Dept. of Trans. PROGRESS Serial No. Contract No. 07-142-07-39 04-470804 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 41% 18% 04-ALA-580-0.0/2.7 Federal Project: NONE Progress payment No. 10 Payment period ending: 05-20-07 DE SILVA GATES M C M A JOINT VENTURE OF DE SILVA GATES CONSTRUCTION AND M C M CONSTRUCTION P O BOX 2909 DUBLIN CA 94568Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 5,300,934.31 156,238.43 2.a. Extra Work 1,257,124.40 43,069.80 b. Adjustment Comp. -3,000.00 0.00 3. Materials on Hand 287,956.04 119,612.00 4. Earned Subject to Retention 6,843,014.75 318,920.23 5. Mobilization 1,786,000.00 0.00 6. Total Work Completed 8,341,058.71 7. Deductions -9,612.44 0.00 8. a.Contract Retentions -361,882.78 0.00 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 8,257,519.53 318,920.23 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 318,920.23