Dept. of Trans. PROGRESS Serial No. Contract No. 07-170-07-58 04-470804 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 47% 22% 04-ALA-580-0.0/2.7 Federal Project: NONE Progress payment No. 11 Payment period ending: 06-19-07 DE SILVA GATES M C M A JOINT VENTURE OF DE SILVA GATES CONSTRUCTION AND M C M CONSTRUCTION P O BOX 2909 DUBLIN CA 94568Escrow No. 02302 Total Estimate This Estimate 1. Contract Itms Without Mobil. 6,552,244.38 1,251,310.07 2.a. Extra Work 1,264,495.82 7,371.42 b. Adjustment Comp. -3,000.00 0.00 3. Materials on Hand 465,477.11 177,521.07 4. Earned Subject to Retention 8,279,217.31 1,436,202.56 5. Mobilization 1,786,000.00 0.00 6. Total Work Completed 9,599,740.20 7. Deductions -9,612.44 0.00 8. a.Contract Retentions -413,960.87 -52,078.09 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 9,641,644.00 1,384,124.47 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,384,124.47