Dept. of Trans. PROGRESS Serial No. Contract No. 07-205-08-00 04-470804 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 51% 26% 04-ALA-580-0.0/2.7 Federal Project: NONE Progress payment No. 12 Payment period ending: 07-20-07 DE SILVA GATES M C M A JOINT VENTURE OF DE SILVA GATES CONSTRUCTION AND M C M CONSTRUCTION P O BOX 2909 DUBLIN CA 94568Escrow No. 02302 Total Estimate This Estimate 1. Contract Itms Without Mobil. 7,555,591.38 1,003,347.00 2.a. Extra Work 1,264,495.82 0.00 b. Adjustment Comp. -3,000.00 0.00 3. Materials on Hand 417,870.13 -47,606.98 4. Earned Subject to Retention 9,234,957.33 955,740.02 5. Mobilization 1,786,000.00 0.00 6. Total Work Completed 10,603,087.20 7. Deductions -10,967.64 -1,355.20 8. a.Contract Retentions -461,747.87 -47,787.00 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 10,548,241.82 906,597.82 10. Reduction Amt to Escrow 11. Payment to Escrow 461,740.00 12. Net Pymt. this Estimate 906,597.82