Dept. of Trans. PROGRESS Serial No. Contract No. 07-234-13-37 04-470804 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 57% 29% 04-ALA-580-0.0/2.7 Federal Project: NONE Progress payment No. 13 Payment period ending: 08-20-07 DE SILVA GATES M C M A JOINT VENTURE OF DE SILVA GATES CONSTRUCTION AND M C M CONSTRUCTION P O BOX 2909 DUBLIN CA 94568Escrow No. 02302 Total Estimate This Estimate 1. Contract Itms Without Mobil. 8,746,809.92 1,191,218.54 2.a. Extra Work 1,352,500.33 88,004.51 b. Adjustment Comp. -21,576.00 -18,576.00 3. Materials on Hand 267,970.42 -149,899.71 4. Earned Subject to Retention 10,345,704.67 1,110,747.34 5. Mobilization 1,880,000.00 94,000.00 6. Total Work Completed 11,957,734.25 7. Deductions -10,967.64 0.00 8. a.Contract Retentions -517,285.23 -55,537.36 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 11,697,451.80 1,149,209.98 10. Reduction Amt to Escrow 11. Payment to Escrow 517,280.00 12. Net Pymt. this Estimate 1,149,209.98