Dept. of Trans. PROGRESS Serial No. Contract No. 07-267-08-11 04-470804 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 63% 33% 04-ALA-580-0.0/2.7 Federal Project: NONE Progress payment No. 14 Payment period ending: 09-20-07 DE SILVA GATES M C M A JOINT VENTURE OF DE SILVA GATES CONSTRUCTION AND M C M CONSTRUCTION P O BOX 2909 DUBLIN CA 94568Escrow No. 02302 Total Estimate This Estimate 1. Contract Itms Without Mobil. 9,930,365.82 1,183,555.90 2.a. Extra Work 1,359,981.61 7,481.28 b. Adjustment Comp. -21,576.00 0.00 3. Materials on Hand 165,023.22 -102,947.20 4. Earned Subject to Retention 11,433,794.65 1,088,089.98 5. Mobilization 1,880,000.00 0.00 6. Total Work Completed 13,148,771.43 7. Deductions -12,167.64 -1,200.00 8. a.Contract Retentions -571,689.73 -54,404.50 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 12,729,937.28 1,032,485.48 10. Reduction Amt to Escrow 11. Payment to Escrow 571,680.00 12. Net Pymt. this Estimate 1,032,485.48