Dept. of Trans. PROGRESS Serial No. Contract No. 07-330-08-40 04-470804 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 73% 39% 04-ALA-580-0.0/2.7 Federal Project: NONE Progress payment No. 16 Payment period ending: 11-20-07 DE SILVA GATES M C M A JOINT VENTURE OF DE SILVA GATES CONSTRUCTION AND M C M CONSTRUCTION P O BOX 2909 DUBLIN CA 94568Escrow No. 02302 Total Estimate This Estimate 1. Contract Itms Without Mobil. 12,128,038.89 1,335,518.27 2.a. Extra Work 1,463,924.18 6,340.86 b. Adjustment Comp. -21,576.00 0.00 3. Materials on Hand 204,592.66 -79,975.56 4. Earned Subject to Retention 13,774,979.73 1,261,883.57 5. Mobilization 1,880,000.00 0.00 6. Total Work Completed 15,450,387.07 7. Deductions -12,167.64 0.00 8. a.Contract Retentions -688,748.99 -63,094.18 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 14,954,063.10 1,198,789.39 10. Reduction Amt to Escrow 11. Payment to Escrow 688,740.00 12. Net Pymt. this Estimate 1,198,789.39