Dept. of Trans. PROGRESS Serial No. Contract No. 07-358-09-47 04-470804 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 77% 42% 04-ALA-580-0.0/2.7 Federal Project: NONE Progress payment No. 17 Payment period ending: 12-20-07 DE SILVA GATES M C M A JOINT VENTURE OF DE SILVA GATES CONSTRUCTION AND M C M CONSTRUCTION P O BOX 2909 DUBLIN CA 94568Escrow No. 02302 Total Estimate This Estimate 1. Contract Itms Without Mobil. 13,008,410.23 880,371.34 2.a. Extra Work 1,479,397.23 15,473.05 b. Adjustment Comp. -21,576.00 0.00 3. Materials on Hand 233,128.66 28,536.00 4. Earned Subject to Retention 14,699,360.12 924,380.39 5. Mobilization 1,880,000.00 0.00 6. Total Work Completed 16,346,231.46 7. Deductions -37,467.64 -25,300.00 8. a.Contract Retentions -734,968.01 -46,219.02 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 15,806,924.47 852,861.37 10. Reduction Amt to Escrow 11. Payment to Escrow 734,960.00 12. Net Pymt. this Estimate 852,861.37