Dept. of Trans. PROGRESS Serial No. Contract No. 08-056-07-40 04-470804 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 82% 47% 04-ALA-580-0.0/2.7 Federal Project: NONE Progress payment No. 19 Payment period ending: 02-20-08 DE SILVA GATES M C M A JOINT VENTURE OF DE SILVA GATES CONSTRUCTION AND M C M CONSTRUCTION P O BOX 2909 DUBLIN CA 94568Escrow No. 02302 Total Estimate This Estimate 1. Contract Itms Without Mobil. 14,046,033.58 112,176.27 2.a. Extra Work 1,576,665.67 72,325.06 b. Adjustment Comp. -20,711.50 0.00 3. Materials on Hand 32,495.53 12,553.40 4. Earned Subject to Retention 15,634,483.28 197,054.73 5. Mobilization 1,880,000.00 0.00 6. Total Work Completed 17,481,987.75 7. Deductions -47,467.64 -10,000.00 8. a.Contract Retentions -781,724.16 -9,852.73 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 16,685,291.48 177,202.00 10. Reduction Amt to Escrow 11. Payment to Escrow 781,720.00 12. Net Pymt. this Estimate 177,202.00