Dept. of Trans. PROGRESS Serial No. Contract No. 08-084-14-36 04-470804 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 85% 50% 04-ALA-580-0.0/2.7 Federal Project: NONE Progress payment No. 20 Payment period ending: 03-20-08 DE SILVA GATES M C M A JOINT VENTURE OF DE SILVA GATES CONSTRUCTION AND M C M CONSTRUCTION P O BOX 2909 DUBLIN CA 94568Escrow No. 02302 Total Estimate This Estimate 1. Contract Itms Without Mobil. 14,538,371.08 492,337.50 2.a. Extra Work 1,602,963.05 26,297.38 b. Adjustment Comp. -7,175.59 13,535.91 3. Materials on Hand 32,495.53 0.00 4. Earned Subject to Retention 16,166,654.07 532,170.79 5. Mobilization 1,880,000.00 0.00 6. Total Work Completed 18,014,158.54 7. Deductions -33,167.64 14,300.00 8. a.Contract Retentions -808,332.70 -26,608.54 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 17,205,153.73 519,862.25 10. Reduction Amt to Escrow 11. Payment to Escrow 808,330.00 12. Net Pymt. this Estimate 519,862.25