Dept. of Trans. PROGRESS Serial No. Contract No. 08-114-13-33 04-470804 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 88% 54% 04-ALA-580-0.0/2.7 Federal Project: NONE Progress payment No. 21 Payment period ending: 04-20-08 DE SILVA GATES M C M A JOINT VENTURE OF DE SILVA GATES CONSTRUCTION AND M C M CONSTRUCTION P O BOX 2909 DUBLIN CA 94568Escrow No. 02302 Total Estimate This Estimate 1. Contract Itms Without Mobil. 15,106,550.47 568,179.39 2.a. Extra Work 1,635,975.31 33,012.26 b. Adjustment Comp. -7,175.59 0.00 3. Materials on Hand 20,764.53 -11,731.00 4. Earned Subject to Retention 16,756,114.72 589,460.65 5. Mobilization 1,880,000.00 0.00 6. Total Work Completed 18,615,350.19 7. Deductions -33,167.64 0.00 8. a.Contract Retentions -837,805.74 -29,473.04 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 17,765,141.34 559,987.61 10. Reduction Amt to Escrow 11. Payment to Escrow 837,800.00 12. Net Pymt. this Estimate 559,987.61