Dept. of Trans. PROGRESS Serial No. Contract No. 08-143-08-46 04-470804 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 91% 57% 04-ALA-580-0.0/2.7 Federal Project: NONE Progress payment No. 22 Payment period ending: 05-20-08 DE SILVA GATES M C M A JOINT VENTURE OF DE SILVA GATES CONSTRUCTION AND M C M CONSTRUCTION P O BOX 2909 DUBLIN CA 94568Escrow No. 02302 Total Estimate This Estimate 1. Contract Itms Without Mobil. 15,648,736.70 542,186.23 2.a. Extra Work 1,695,046.47 59,071.16 b. Adjustment Comp. -7,175.59 0.00 3. Materials on Hand 20,764.53 0.00 4. Earned Subject to Retention 17,357,372.11 601,257.39 5. Mobilization 1,880,000.00 0.00 6. Total Work Completed 19,216,607.58 7. Deductions -43,167.64 -10,000.00 8. a.Contract Retentions -867,868.61 -30,062.87 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 18,326,335.86 561,194.52 10. Reduction Amt to Escrow 11. Payment to Escrow 867,860.00 12. Net Pymt. this Estimate 561,194.52