Dept. of Trans. PROGRESS Serial No. Contract No. 08-169-11-09 04-470804 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 93% 61% 04-ALA-580-0.0/2.7 Federal Project: NONE Progress payment No. 23 Payment period ending: 06-20-08 DE SILVA GATES M C M A JOINT VENTURE OF DE SILVA GATES CONSTRUCTION AND M C M CONSTRUCTION P O BOX 2909 DUBLIN CA 94568Escrow No. 02302 Total Estimate This Estimate 1. Contract Itms Without Mobil. 16,160,001.70 511,265.00 2.a. Extra Work 1,770,207.19 75,160.72 b. Adjustment Comp. -7,175.59 0.00 3. Materials on Hand 20,764.53 0.00 4. Earned Subject to Retention 17,943,797.83 586,425.72 5. Mobilization 1,880,000.00 0.00 6. Total Work Completed 19,803,033.30 7. Deductions -43,167.64 0.00 8. a.Contract Retentions -897,189.89 -29,321.28 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 18,883,440.30 557,104.44 10. Reduction Amt to Escrow 11. Payment to Escrow 897,180.00 12. Net Pymt. this Estimate 557,104.44