Dept. of Trans. PROGRESS Serial No. Contract No. 03-330-10-11 04-4874R4 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 64% 44% 04-SCL-87-7.1/7.8 Federal Project: ACNH-S087(23) Progress payment No. 14 Payment period ending: 11-20-03 GRANITE CONSTRUCTION COMPANY P O BOX 50085 WATSONVILLE CA 950775085 Escrow No. 02010 Total Estimate This Estimate 1. Contract Itms Without Mobil. 11,491,012.93 1,146,641.02 2.a. Extra Work 793,031.39 252,062.20 b. Adjustment Comp. 6,875.00 6,875.00 3. Materials on Hand 55,039.20 52,411.36 4. Earned Subject to Retention 12,345,958.52 1,457,989.58 5. Mobilization 2,135,000.00 0.00 6. Total Work Completed 14,425,919.32 7. Deductions 8. a.Contract Retentions -617,297.93 -72,899.48 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 13,863,660.59 1,385,090.10 10. Reduction Amt to Escrow 11. Payment to Escrow 617,290.00 12. Net Pymt. this Estimate 1,385,090.10