Dept. of Trans. SUPPLEMENTAL Serial No. Contract No. 04-119-15-46 04-4874R4 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 76% 52% 04-SCL-87-7.1/7.8 Federal Project: ACNH-S087(23) Progress payment No. 20 Payment period ending: 04-20-04 GRANITE CONSTRUCTION COMPANY P O BOX 50085 WATSONVILLE CA 950775085 Escrow No. 02010 Total Estimate This Estimate 1. Contract Itms Without Mobil. 14,416,685.83 65,698.99 2.a. Extra Work 1,057,829.64 0.00 b. Adjustment Comp. 7,062.20 0.00 3. Materials on Hand 90,026.00 0.00 4. Earned Subject to Retention 15,571,603.67 65,698.99 5. Mobilization 2,135,000.00 0.00 6. Total Work Completed 17,616,577.67 7. Deductions 8. a.Contract Retentions -778,580.18 -3,284.95 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 16,928,023.49 62,414.04 10. Reduction Amt to Escrow 11. Payment to Escrow 778,580.00 12. Net Pymt. this Estimate 62,414.04