Dept. of Trans. PROGRESS Serial No. Contract No. 04-141-13-32 04-4874R4 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 78% 56% 04-SCL-87-7.1/7.8 Federal Project: ACNH-S087(23) Progress payment No. 21 Payment period ending: 05-20-04 GRANITE CONSTRUCTION COMPANY P O BOX 50085 WATSONVILLE CA 950775085 Escrow No. 02010 Total Estimate This Estimate 1. Contract Itms Without Mobil. 14,948,300.66 531,614.83 2.a. Extra Work 1,168,210.89 110,381.25 b. Adjustment Comp. 7,062.20 0.00 3. Materials on Hand 116,424.92 26,398.92 4. Earned Subject to Retention 16,239,998.67 668,395.00 5. Mobilization 2,135,000.00 0.00 6. Total Work Completed 18,258,573.75 7. Deductions 8. a.Contract Retentions -811,999.93 -33,419.75 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 17,562,998.74 634,975.25 10. Reduction Amt to Escrow 11. Payment to Escrow 811,990.00 12. Net Pymt. this Estimate 634,975.25