Dept. of Trans. PROGRESS Serial No. Contract No. 02-291-13-02 04-4874V4 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 58% 36% 04-SCL-87-6.5/8.9 Federal Project: ACNH-S087(17) Progress payment No. 08 Payment period ending: 10-20-02 WATKIN AND BORTOLUSSI INC 77 LARKSPUR ST SAN RAFAEL CA 94901 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 392,041.00 1,240.00 2.a. Extra Work 6,002.36 511.74 b. Adjustment Comp. 500.00 0.00 3. Materials on Hand 4. Earned Subject to Retention 398,543.36 1,751.74 5. Mobilization 75,800.00 0.00 6. Total Work Completed 474,343.36 7. Deductions 8. a.Contract Retentions -19,927.17 -87.59 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 454,416.19 1,664.15 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,664.15