Dept. of Trans. PROGRESS Serial No. Contract No. 04-202-11-39 04-487604 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 40% 32% 04-SCL-101-39.3/41.0 Federal Project: ACNH-Q101(44) Progress payment No. 09 Payment period ending: 07-20-04 PAVEX CONSTRUCTION DIVISION 330 BLOMQUIST ST REDWOOD CITY CA 94063 Escrow No. 02142 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2,839,039.53 138,191.75 2.a. Extra Work b. Adjustment Comp. -3,260.74 -3,260.74 3. Materials on Hand 4. Earned Subject to Retention 2,835,778.79 134,931.01 5. Mobilization 779,000.00 0.00 6. Total Work Completed 3,614,778.79 7. Deductions 8. a.Contract Retentions -165,089.59 0.00 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 3,449,689.20 134,931.01 10. Reduction Amt to Escrow 11. Payment to Escrow 165,080.00 12. Net Pymt. this Estimate 134,931.01