Dept. of Trans. PROGRESS Serial No. Contract No. 06-080-10-00 04-487604 PROGRESS PAYMENT VOUCHER %complete: %time: Location: PEP SAT 04-SCL-101-39.3/41.0 Federal Project: ACNH-Q101(44) Progress payment No. 29 Payment period ending: 03-20-06 PAVEX CONSTRUCTION DIVISION 330 BLOMQUIST ST REDWOOD CITY CA 94063 Escrow No. 02142 Total Estimate This Estimate 1. Contract Itms Without Mobil. 8,348,093.97 830.00 2.a. Extra Work 624,335.66 0.00 b. Adjustment Comp. 110,169.06 0.00 3. Materials on Hand 4. Earned Subject to Retention 9,082,598.69 830.00 5. Mobilization 820,000.00 0.00 6. Total Work Completed 9,902,598.69 7. Deductions -4,909.20 0.00 8. a.Contract Retentions -454,129.93 -41.50 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 9,443,559.56 788.50 10. Reduction Amt to Escrow 11. Payment to Escrow 453,920.00 12. Net Pymt. this Estimate 788.50