Dept. of Trans. PROGRESS Serial No. Contract No. 13-057-09-13 04-4A07U4 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 14% 8% 04-ALA-580-R4.7/8.2 Federal Project: ACIM-5801(51) Progress payment No. 06 Payment period ending: 02-20-13 DESILVA GATES CONSTRUCTION LP P O BOX 2909 DUBLIN CA 94568 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 3,272,539.89 -58,000.00 2.a. Extra Work 90,808.93 61,879.94 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 3,363,348.82 3,879.94 5. Mobilization 1,865,000.00 0.00 6. Total Work Completed 5,228,348.82 7. Deductions -38,150.00 0.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 5,190,198.82 3,879.94 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 3,879.94