Dept. of Trans. PROGRESS Serial No. Contract No. 13-325-07-17 04-4A07U4 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 35% 37% 04-ALA-580-R4.7/8.2 Federal Project: ACIM-5801(51) Progress payment No. 15 Payment period ending: 11-20-13 DESILVA GATES CONSTRUCTION LP P O BOX 2909 DUBLIN CA 94568 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 9,067,846.29 995,209.09 2.a. Extra Work 972,523.45 31,301.66 b. Adjustment Comp. 3. Materials on Hand 152,254.91 77,232.39 4. Earned Subject to Retention 10,192,624.65 1,103,743.14 5. Mobilization 3,543,500.00 0.00 6. Total Work Completed 13,583,869.74 7. Deductions -65,650.00 -12,500.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 13,670,474.65 1,091,243.14 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,091,243.14