Dept. of Trans. PROGRESS Serial No. Contract No. 14-016-07-19 04-4A07U4 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 36% 35% 04-ALA-580-R4.7/8.2 Federal Project: ACIM-5801(51) Progress payment No. 17 Payment period ending: 01-20-14 DESILVA GATES CONSTRUCTION LP P O BOX 2909 DUBLIN CA 94568 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 9,146,375.84 -107,402.00 2.a. Extra Work 1,192,332.88 139,184.44 b. Adjustment Comp. -3,912.00 -3,912.00 3. Materials on Hand 149,202.91 51,377.95 4. Earned Subject to Retention 10,483,999.63 79,248.39 5. Mobilization 3,543,500.00 0.00 6. Total Work Completed 13,878,296.72 7. Deductions -96,665.46 10,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 13,930,834.17 89,248.39 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 89,248.39