Dept. of Trans. PROGRESS Serial No. Contract No. 14-265-08-16 04-4A07U4 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 43% 53% 04-ALA-580-R4.7/8.2 Federal Project: ACIM-5801(51) Progress payment No. 25 Payment period ending: 09-20-14 DESILVA GATES CONSTRUCTION LP P O BOX 2909 DUBLIN CA 94568 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 11,933,112.74 426,560.00 2.a. Extra Work 1,517,051.30 16,903.18 b. Adjustment Comp. 135,712.71 0.00 3. Materials on Hand 122,405.65 51,731.40 4. Earned Subject to Retention 13,708,282.40 495,194.58 5. Mobilization 3,543,500.00 0.00 6. Total Work Completed 17,129,376.75 7. Deductions -56,423.10 -773.10 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 17,195,359.30 494,421.48 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 494,421.48