Dept. of Trans. PROGRESS Serial No. Contract No. 14-325-09-43 04-4A07U4 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 47% 57% 04-ALA-580-R4.7/8.2 Federal Project: ACIM-5801(51) Progress payment No. 27 Payment period ending: 11-20-14 DESILVA GATES CONSTRUCTION LP P O BOX 2909 DUBLIN CA 94568 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 13,431,920.19 791,829.25 2.a. Extra Work 1,643,565.13 42,997.52 b. Adjustment Comp. 135,712.71 0.00 3. Materials on Hand 83,087.54 0.00 4. Earned Subject to Retention 15,294,285.57 834,826.77 5. Mobilization 3,543,500.00 0.00 6. Total Work Completed 18,754,698.03 7. Deductions -56,423.10 0.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 18,781,362.47 834,826.77 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 834,826.77