Dept. of Trans. PROGRESS Serial No. Contract No. 15-357-07-26 04-4A07U4 PROGRESS PAYMENT VOUCHER %complete: %time: 93% 83% Location: Federal Project: 04-ALA-580-R4.7/8.2 ACIM-5801(51) Progress payment No. 040 Payment period ending: 12-20-15 DESILVA GATES CONSTRUCTION LP P O BOX 2909 DUBLIN CA 94568 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 28,712,375.87 1,586,775.39 2. a. Extra Work 6,527,027.31 58,584.85 b. Adustment Comp. 501,924.97 4,249.00 3. Materials on Hand 4. Earned Subject to Retention 35,741,328.15 1,649,609.24 5. Mobilization 3,730,000.00 0.00 6. Total Work Completed 39,471,328.15 7. Deductions -896,634.86 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 38,574,693.29 1,649,609.24 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,649,609.24