Dept. of Trans. PROGRESS Serial No. Contract No. 16-020-16-56 04-4A07U4 PROGRESS PAYMENT VOUCHER %complete: %time: 91% 84% Location: Federal Project: 04-ALA-580-R4.7/8.2 ACIM-5801(51) Progress payment No. 041 Payment period ending: 01-20-16 DESILVA GATES CONSTRUCTION LP P O BOX 2909 DUBLIN CA 94568 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 28,572,718.14 -139,657.73 2. a. Extra Work 6,688,309.81 161,282.50 b. Adustment Comp. -267,228.82 -769,153.79 3. Materials on Hand 31,910.00 31,910.00 4. Earned Subject to Retention 35,025,709.13 -715,619.02 5. Mobilization 3,730,000.00 0.00 6. Total Work Completed 38,723,799.13 7. Deductions -56,423.10 840,211.76 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 38,699,286.03 124,592.74 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 124,592.74