Dept. of Trans. PROGRESS Serial No. Contract No. 15-352-15-32 04-4A0904 PROGRESS PAYMENT VOUCHER %complete: %time: 93% 31% Location: Federal Project: 04-NAP-29-47.0/47.2 STP-P029(117) Progress payment No. 008 Payment period ending: 12-20-15 GORDON N. BALL, INC. 333 CAMILLE AVENUE ALAMO CA 94507 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 3,898,953.21 137,220.96 2. a. Extra Work 64,667.52 28,688.77 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 3,963,620.73 165,909.73 5. Mobilization 460,000.00 0.00 6. Total Work Completed 4,423,620.73 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 4,423,620.73 165,909.73 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 165,909.73