Dept. of Trans. PROGRESS Serial No. Contract No. 25-232-14-15 04-4A1304 PROGRESS PAYMENT VOUCHER %complete: %time: 61% 42% Location: Federal Project: 04-SON-101-18.5/18.5 NH Progress payment No. 019 Payment period ending: 08-20-25 GHILOTTI CONSTRUCTION CO INC 246 GHILOTTI AVENUE SANTA ROSA CA 95407 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 13,427,988.12 2,285,816.12 2. a. Extra Work 362,053.95 146,000.00 b. Adustment Comp. 3. Materials on Hand 336,959.63 -594,073.00 4. Earned Subject to Retention 14,127,001.70 1,837,743.12 5. Mobilization 2,288,800.00 114,440.00 6. Total Work Completed 16,078,842.07 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 16,415,801.70 1,952,183.12 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,952,183.12