Dept. of Trans. FINAL Serial No. Contract No. 11-049-11-33 04-4A1704 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 04-SON-128-0.0/3.3 Federal Project: NONE Progress payment No. 04 Payment period ending: 07-19-10 DREAMBUILDER 1361 E GARTEN DRIVE PLACENTIA CA 92870 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 278,744.41 0.00 2.a. Extra Work 21,414.24 0.00 b. Adjustment Comp. 3,974.61 0.00 3. Materials on Hand 4. Earned Subject to Retention 304,133.26 0.00 5. Mobilization 8,000.00 0.00 6. Total Work Completed 312,133.26 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 312,133.26 0.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 0.00