Dept. of Trans. FINAL Serial No. Contract No. 09-029-06-20 04-4A2004 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 04-SON-121-9.8/11.6 Federal Project: NONE Progress payment No. 04 Payment period ending: 09-23-08 TEAM GHILOTTI INC 2531 PETALUMA BOULEVARD SOUTH PETALUMA CA 94952 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 611,452.64 0.00 2.a. Extra Work 47,612.13 9,112.13 b. Adjustment Comp. 22,260.81 0.00 3. Materials on Hand 4. Earned Subject to Retention 681,325.58 9,112.13 5. Mobilization 6. Total Work Completed 681,325.58 7. Deductions 8. a.Contract Retentions -31,653.71 0.00 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 31,653.71 0.00 9. Total pay to Contractor 681,325.58 9,112.13 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 9,112.13