Dept. of Trans. PROGRESS Serial No. Contract No. 10-300-10-44 04-4A2304 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 76% 96% 04-SON-37-0.9/2.6 Federal Project: NONE Progress payment No. 01 Payment period ending: 10-20-10 VICTORY ENGINEERS, INC. 10266 HIGHWAY 41 MADERA, CA 93636 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 163,870.12 163,870.12 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 163,870.12 163,870.12 5. Mobilization 6. Total Work Completed 163,870.12 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. -16,387.01 -16,387.01 c. Reduction after 95% Comp. 9. Total pay to Contractor 147,483.11 147,483.11 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 147,483.11