Dept. of Trans. PROGRESS Serial No. Contract No. 13-235-15-54 04-4A3304 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 68% 44% 04-SCL-101-49.0/52.2 Federal Project: NONE Progress payment No. 20 Payment period ending: 08-20-13 O C JONES AND SONS INC 1520 FOURTH STREET BERKELEY CA 94710 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 20,337,700.02 539,594.78 2.a. Extra Work 1,691,423.62 41,995.35 b. Adjustment Comp. 2,676,531.72 0.00 3. Materials on Hand 986,209.51 -11,505.61 4. Earned Subject to Retention 25,691,864.87 570,084.52 5. Mobilization 1,700,000.00 0.00 6. Total Work Completed 26,405,655.36 7. Deductions -9,586.03 0.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 27,382,278.84 570,084.52 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 570,084.52