Dept. of Trans. PROGRESS Serial No. Contract No. 15-237-08-21 04-4A3424 PROGRESS PAYMENT VOUCHER %complete: %time: 91% 96% Location: Federal Project: 04-ALA-24-5.6 HSNH-X001(586) 04-ALA-580-20.7 04-ALA-580-44.7 Progress payment No. 002 Payment period ending: 08-20-15 PETERSON-CHASE GENERAL ENGINEERING CONSTRUCTION, INC. 1792 KAISER AVENUE IRVINE CA 92614 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 531,036.00 175,406.20 2. a. Extra Work 20,205.00 20,205.00 b. Adustment Comp. 9,131.54 9,131.54 3. Materials on Hand 4. Earned Subject to Retention 560,372.54 204,742.74 5. Mobilization 51,000.00 0.00 6. Total Work Completed 611,372.54 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 611,372.54 204,742.74 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 204,742.74